In Nizhnekamsk, 83% of the heating networks planned for 2026 have been updated.
In Nizhnekamsk, the update of utility networks continues. Since the beginning of the year, specialists have replaced 46.5 kilometers of heating networks out of the planned 56 kilometers — this is 83% of the total volume of work. As reported by the director of the branch of JSC "Tatenergo" — "Nizhnekamsk Heating Networks" Ilnar Galimzyanov, the installation of new pipes is planned to be completed by the end of August. A total of 54 facilities are included in the program for network replacement, along with the renovation of the facades of 21 central heating points and the updating of other equipment. Sixteen contracting organizations are involved in the work. Currently, due to the repairs, hot water supply is temporarily turned off in 246 houses. The restoration of supply is planned in almost all buildings by the end of August, after which specialists will focus on landscaping the areas. This year, nearly 2.6 billion rubles have been allocated for the modernization of housing and communal services in Nizhnekamsk as part of the utility infrastructure renewal program. With the funds from "Tatenergo," the total financing will reach 3.7 billion rubles. Over three summer repair seasons, the city plans to replace almost 122.5 kilometers of heating networks — about 16.5% of the entire length of the system. Photo: minstroy.tatarstan.ru
Другие Новости Казани (Казань716)
In Nizhnekamsk, 83% of the heating networks planned for 2026 have been updated.
In Nizhnekamsk, the upgrade of utility networks continues. Since the beginning of the year, specialists have replaced 46.5 kilometers of heating networks out of the planned 56 kilometers — this is 83% of the total volume of work. 17.08.2026. GTRK Tatarstan. Republic of Tatarstan. Kazan.